Thursday, May 8, 2014
Wednesday, May 7, 2014
Bricks!
7/5/2014
Received a message from our next door neighbour that our bricks arrived today. Also received a text from our SS saying that the roof frames have been completed. I hope my wife took some pics today as it is dark by the time I get home.Tuesday, May 6, 2014
Windows Arrive
6/5/2014
Didn't get any photo's today as I was working. Had a look tonight and seen we have windows sitting in the garage. The roof trusses are well advanced and maybe all framing will be completed by the weekend. Over the next 6 weeks I'm either on holidays or nightshift so I will be able to watch the house progress.Friday, May 2, 2014
Frames Progressing
2/5/2014
More progress today and wow it's BIG. Had a chat with the tradespeople and they said a crane will install the roof trusses on Monday weather permitting. They even moved the door frame out of the mud for us. It's starting to look like a house now.
The door frame is now behind the red sheeting and out of the mud.
Thursday, May 1, 2014
Framed!
1/5/2014
May Day and we have framing started. Looks like a big Mechano set waiting to be put together. My kids would love to have a crack at! The front door frame also arrived and with rain forecast over the next few days, I hope it doesn't damage it.
Not sure about this being exposed to the elements.
Wednesday, April 23, 2014
Frames have Arrived!
24/4/2014
The frames arrived today and also noticed we have power and water connected. Most probably won't start framing until Monday or Tuesday next week letting the slab cure properly.Termite Barrier
23/4/2014
The Termite barrier was laid down today and a mini excavator flatten the dirt out the front. I spoke with the operator and he said the frames are to arrive tomorrow.